Maji Matamu meaning sweet water in Kiswahili is a project of Garden of Hope International. We have experienced first hand the desperate need of clean water in the drought areas of Kitui and Machakos in eastern Kenya. We have chosen to partner with the Kangonde community of Machakos Kenya to drill a borehole at the site of a future missions station which will include the completion of a children's home. For more information please write: majimatamukenya@gmail.com
Friday, May 18, 2012
THE OFFICIAL ITEMIZED QUOTATION
Drilling for life Giving life one well at a time 1
P.O. Box 4414 – 01002 Thika, Kenya
Tel: 020 - 230 88 55 / 0719 107 553
dflkenya@drillingforlife.org
www.drillingforlife.org
March 16, 2012
BEVERLY MILLS
MAJI MATAMU PROJECT
KANGONDE - MWINGI
Bills of Quantities
For drilling one borehole of 120m depth at Kangonde – Mwingi
180M DEPTH FULLY CASED
180M DEPTH OPEN
BOREHOLE DRILLING ..KENYA SHILLINGS/ US DOLLARS
Mobilization and Demobilization:
Allow for the cost of transporting all equipment and personnel to site and demobilization at completion of contract-40,000KS/$485.00
Setting and dismantling of the rig at the drilling site-15,000KS/$180.00
Drilling 8" diameter borehole from 0 - 30m depth-66,000KS/$795.00/fullycased-220,000ks/$2,610.00
Drilling 6" diameter borehole from 30 - 180m depth-300,000KS/$3,615
Water & Foam: Water for drilling & camp use & drilling foam- 20,000KS/$241.00
Geological Sampling & Report-17,500KS/$215.00
Casings: Supply & install 10" dia temporary protective steel starter casing-18,000KS/$220.00
Supply & Install 152mm (6") dia plain steel casings 81,000KS/$975.00/fully cased-194,000ks/$2,300.00
Supply & Install 152mm (6") dia machine cut steel (slotted) casings-0/full cased-141,000ks/$1,673.00
Gravel Pack: Supply & Install 2-4mm gravel pack-0-full cased-19,500ks/$230.00
Well Construction: Provide materials & construct concrete surface plug around casing & top slab with well cap-25,000 KS/$302
Well Development/Cleaning of borehole: Allow for borehole development work (surging by air of completed well until the water is clean - approx 4hrs)-68,000KS/$820.00
Test Pumping: Supply & Mobilization of unit- 20,000KS/$241.00
Installation & Removal of unit-13,000KS/$165.00
Test Pumping for 24hrs-60,000KS/$725.00
Recovery after test-6,000KS/$73.00
Full Chemical & Bacteriological Analysis of extracted water-15,000KS/$180.00
TOTAL OPEN HOLE-765,000 KS/$ 9,225.00 FULLY CASED-933,500/$11,075.00
TOTAL PHASE II 1,570,000KS/$18,624.00
PHASE III: EQUIPPING OF BOREHOLE WITH PUMP & ACCESSORIES
Pump Supply & Installation: Supply & Installation of Grundfos pump SP5A-25 complete with 2.2kw motor
230,000KS/
Pump Accessories Supply & Installation: control panel, electrodes, electrode cable, underground cables, float switch & various installation accessories-490,000KS/$
Supply & Installation of Generator: Lister Petter Electric Start Generator 3 phase - 5.8KVA. (NB: Can also opt to power pump by electricity if available or solar panel)- 850,000KS/$10,085.00
TOTAL PHASE III- OPEN HOLE 2,215,000KS/$26,275.00 FULLY CASED2,503,500KS/$29,700.00
GRAND TOTAL- $35,000-$48,395 DEPENDING ON FOREIGN EXCHANGE RATE..AND WHAT WORK AND EQUIPMENT IN PHASE 3 CAN BE PURCHASED BY US DIRECTLY AND INSTALLED BY US, VERSES THE DRILLING COMPANY..